This bridge replacement included pile driving work, removal of 250 tons of structural steel, furnishing and erecting 200 tons of structural steel and miscellaneous retaining wall and bridge abutment concrete work. The installation of six track jump spans allowing for abutment construction facilitated a limited number of 3-day maximum track outages. This project was completed in January 2007.

 

 
 
 
 
 