IHBRR Bridge 5 Replacement, Calumet City, IL
This three month duration project included a 72 hour weekend shutdown to remove and replace the bridge. ICC completed the 72 hour weekend shutdown in 22 hours, which included an early completion bonus. The advanced work included driving H-piles, installing three new concrete piers & two new concrete abutments. During the weekend shutdown, ICC removed the 125-ton existing bridge and installed ten new concrete box beams. This $1,200,000 project was completed in September 2011.